Turn-Lane Work on U.S. 77 Starts November 16
The TxDOT project at County Road 134, serving the Project Orion site near Burlington, runs in two phases — and drivers should expect delays and detours through fall 2027
Work on the Texas Department of Transportation's Turn Lanes Project on U.S. Highway 77 in northern Milam County is set to begin Monday, November 16, according to Precinct 2 County Commissioner James Denman.
The project builds turn lanes on U.S. 77 where County Road 134 meets the highway, at the northern and southern access points for the SBE DC "Project Orion" site near Burlington. A project site map shows the work organized around two turn-lane improvements — a northern Highway 77/CR 134 improvement and a southern Highway 77/CR 134 improvement — with site access roads using CR 133, CR 134, and CR 354. The map also notes that the CR 133 and CR 355 road segment, shown in yellow, was de-scoped by the owner on July 9, 2026.
Phase 1: the southbound side
Phase 1 involves the southbound lane by County Road 134 and is expected to be completed by July 2027, Denman said. Plan sheets for the project's south section show the southbound work there — labeled Block 4 — scheduled to start in December 2026 with completion in March 2027.
Phase 2: the northbound side
Phase 2 takes up the northbound lane, beginning in July 2027 and ending in October 2027. The south section plan sheets show that northbound work — labeled Block 5, built alongside a detour — running on the same July-to-October 2027 schedule, with a rebuilt highway cross-section that includes the new turn lane.
Open by late November 2027
The road should be fully open to traffic by November 22, 2027, Denman said.
A year of construction traffic
Denman cautions motorists to be aware of construction workers and vehicles in the work zone, and to be prepared for delays and detours while the work is underway.
The stretch of U.S. 77 near Burlington, close to the Falls County line, already carries construction traffic for the Project Orion site, and the turn lanes are the highway improvement meant to handle vehicles turning in and out of the site at County Road 134. Drivers who use U.S. 77 through northern Milam County should plan for the work zone to be part of the drive for the next year.
Project maps courtesy of Commissioner James Denman.
Project Maps

Site access roads for the SBE DC – Project Orion site near Burlington, showing the northern and southern Highway 77/CR 134 turn-lane improvements. Map via Commissioner James Denman.

The south section of Highway 77: Block 4 (southbound) is scheduled December 2026–March 2027, and Block 5 (northbound) July–October 2027, with the U.S. Highway 77 typical section below. Plan sheet via Commissioner James Denman.